Construction Activities for the week of July 28, 2016

This Week’s Activities

Site/Structure

  • Commenced Installation of Grease traps at the Fidelity Bank Site.
  • Continued backfill of the lid at Area G.
  • Continued Underground Storm Line Installation South of Area G.
  • Continued Underground Duct Bank Installation South of Area G.

Performing Arts Center

  • Completed first lift of Installation of the North Box Seat Wall.
  • Continued Re-Steel installation on WA Wall—West Stage.
  • Continued prepping for the next lift of the Proscenium Wall.
  • Continued Elevated Slab Installation at Studio Theatre.

Office Tower

  • Continued Installation of Continuous Footings at Office Tower at Area A.
  • Continued Installation of Elevators AE01,AE02,AE03 & AE04 Elevator Pit.
  • Continued first lift of Column Installation.

CIP Parking Deck

  • Completed Townhouse Lid Installation at Area G.
  • Continued Column Installation at Area D.
  • Continued Waterproofing Installation at Area G.
  • Continued Footing Installation at Area D & E.

Precast Parking Deck

  • Completed Topping Slab Installation.
  • Commenced Roofing Installation.
  • Continued Fire Protection Installation.

Roadways

  • Commenced Curb & Gutter Prep for Mt. Vernon and Bluestone Rd.
  • Continued Grading along Mt. Vernon.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.

Next Week’s Activities

Site/Structure

  • Complete Underground Storm Line Installation South of Area G.
  • Complete Underground Duct Bank Installation South of Area G.
  • Continue Backfill of Lid at Area G.
  • Complete Installation of Grease traps at the Fidelity Bank Site.

Performing Arts Center

  • Continue WA Wall Installation—West Stage.
  • Complete Elevated Slab Pour at Studio Theater (Area B1).
  • Continue prepping for the next lift of the Proscenium Wall.

Office Tower

  • Continue Installation of Continuous Footings at Office Tower.
  • Continue Installation of Elevators AE01,AE02,AE03 & AE04 Elevator Pit.
  • Continue Formwork and Column Installation.

CIP Parking Deck

  • Continue Column Installation at Area A & D.
  • Continue Area D & E Footing Installation.
  • Precast Parking Deck
  • Continue Roofing Installation.
  • Continue Fire Protection Installation.

Roadways

  • Continue Underground Utility work on Mt. Vernon working East.
  • Continue Curb & Gutter Installation at Mt.Vernon & Bluestone Rd.
  • Continue Grading along Mt. Vernon—Continuing East.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE.