Construction Activities for the week of July 21, 2016

This Week’s Activities

Site/Structure

  • Completed Water Fountain Piping (Plaza & Interactive) Installation South of Area G.
  • Continued Underground Storm Line installation South of Area G.
  • Continued Underground Duct Bank installation South of Area G.

Performing Arts Center

  • Completed third lift of Column Installation at Area C6.
  • Continued Re-Steel installation on WA Wall—West Stage.
  • Continued prepping for the next lift of the Proscenium Wall.
  • Continued Elevated Slab installation at Studio Theatre.

Office Tower

  • Continued Installation of Continuous Footings at Office Tower at Area A.
  • Continued Installation of Elevators AE01,AE02,AE03 & AE04 Elevator Pit.
  • Continued first lift of Column Installation.

CIP Parking Deck

  • Commence Column Installation at Area D.
  • Completed Slab on Grade at Area F.
  • Continued Waterproofing installation at Area G.
  • Continued Footing Installation at Area D & E.

Precast Parking Deck

  • Completed Barrier Cable Installation.
  • Commenced Roofing Installation.
  • Continued Fire Protection Installation.
  • Continued Topping Slab Installation.

Roadways

  • Continued Grading along Mt. Vernon.
  • Continued Installation of Bluestone Rd.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.

Next Week’s Activities

Site/Structure

  • Complete Underground Storm Line Installation South of Area G.
  • Complete Underground Duct Bank Installation South of Area G.
  • Commence Backfill of Lid at Area G.
  • Commence Installation of Grease traps at the Fidelity Bank Site.

Performing Arts Center

  • Complete 3rd lift on WA Wall—West Stage.
  • Complete Elevated Slab Pour at Studio Theater (Area B1).
  • Continue prepping for the next lift of the Proscenium Wall.

Office Tower

  • Continue Installation of Continuous Footings at Office Tower.
  • Continue Installation of Elevators AE01,AE02,AE03 & AE04 Elevator Pit.
  • Continue Formwork, Column Installation and Rough Grading.

Parking Deck (CIP & Precast)

  • Continue Column Installation at Area D.
  • Continue Area D & E Footing Installation.

Precast Parking Deck

  • Complete Topping Slab Installation.
  • Continue Roofing Installation.
  • Continue Fire Protection Installation.

Roadways

  • Continue Underground Utility work on Mt. Vernon working East.
  • Continue Grading along Mt. Vernon—Continuing East.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE.