Construction Activities for the week of July 14, 2016

This Week’s Construction Activities

Site/Structure

  • Commenced Water Fountain Piping (Plaza & Interactive).
  • Installation South of Area G.
  • Continued Underground Storm Line installation South of Area G.
  • Continued Underground Duct Bank installation South of Area G.

Performing Arts Center

  • Completed Gallery Level Raker, Formwork and Resteel Installation.
  • Commenced Elevated Slab installation at Studio Theatre.
  • Continued third lift of Column Installation at Area C6.
  • Continued Re-Steel installation 3rd lift on WA Wall—West Stage.

Office Tower

  • Continued Installation of Continuous Footings at Office Tower at Area A.
  • Continued Installation of Elevators AE01,AE02,AE03 & AE04 Elevator Pit.
  • Continued first lift of Column Installation.

Parking Deck

  • Completed Slab on Grade at Area F.
  • Completed Column and Shear Wall Installation at Area F.
  • Continued Footing installation at Area D & E.

Roadways

  • Completed Fidelity Bank Retaining Wall Installation.
  • Continued Grading along Mt. Vernon.
  • Continued Installation of Bluestone Rd.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.
  • Continue Precast Deck- Completed Barrier Cable Installation.

Next Week’s Construction Activities

Site/Structure

  • Complete Underground Storm Line Installation South of Area G.
  • Complete Underground Duct Bank Installation South of Area G.
  • Complete Water Fountain Piping (Plaza and Interactive) Installation South of Area G.

Performing Arts Center

  • Complete 3rd lift on WA Wall—West Stage.
  • Complete 3rd lift of Column Installation at Area C6.
  • Continue Formwork and Resteel Installation for Studio Theatre Elevated Slab.

Office Tower

  • Continue Installation of Continuous Footings at Office Tower.
  • Continue Installation of Elevators AE01,AE02,AE03 & AE04 Elevator Pit.
  • Continue Formwork, Column Installation and Rough Grading.

Parking Deck

  • Commence Column Installation at Area D.
  • Continue Area D & E Footing Installation.

Roadways

  • Continue Underground Utility work on Mt. Vernon working East.
  • Continue Grading along Mt. Vernon—Continuing East.
  • Continue Installation of Bluestone Rd.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE.
  • Complete Precast Deck – Topping Slab Installation.