Construction Activities for the Week of January 8, 2016

Construction Activities Impacting Traffic Flow:

Beginning February 1, 2016, the northern-most lane on Johnson Ferry Road, beginning at Ferry Drive and ending just before Sandy Springs Circle, will be closed Monday through Friday between the hours of 9 a.m. and 4 p.m.  Flagmen will direct the traffic flow at that closure, with the closure expected to be in effect through the month, weather permitting.

Beginning February 15, 2015, one lane on Sandy Springs Circle, from Mt Vernon Road to Johnson Ferry Road, will close.   The lane closure will shift as crews work north-to-south along Sandy Springs Circle.    Access to the Springs Landing Shopping Center will remain available throughout this construction period.  Construction is part of a phased program taking place as part of the City Springs development project.

Message boards will be in place, and motorists are urged to plan for a slower pace and use added caution when driving in that area.

The traveling public is encouraged to check the City’s Road Work Advisory page found on the City’s website (shortcut: http://spr.gs/roadwork) and also available through the Sandy Springs Works mobile app (free in the app store).

 

This Week’s On Site Activities

Site / Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck

Performing Arts Center

  • Continued Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and Z4-Z6.
  • Continued PAC Foundations: Gridline WA-WC & O5-O8
  • Commenced Tower Crane Foundation
  • Completed Underdrain Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3
  • Commenced Wall Resteel and Form Erecting at PAC: Gridline WA-WC & W1-W3

Building

  • Continue Deep Foundation Installation at Office Build-ing: Grid Line OD-OK at O8-O4.

Parking Deck

  • Continued Controlled Rock Blasting in CIP Parking Deck: Grid Line PS-PG & P1-P6
  • Continued Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Completed Row 2 Tie-Backs at West Deck: Grid Line PA-PP & P1.
  • Commenced Row 3 Tie-Backs at SWP Deck: Grid Line P7—P11 & PA.1-PE.7
  • Commenced Shotcrete at East Deck: Gridlines TE-PJJ and Z7-O8

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

 

Next Week’s Activities

Site / Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Commence Brick Mock-Up

Performing Arts Center

  • Continued Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and Z4-Z6.
  • Continued PAC Foundations: Gridline WA-WC & O5-O8
  • Commenced Tower Crane Foundation
  • Completed Underdrain Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3
  • Commenced Wall Resteel and Form Erecting at PAC: Gridline WA-WC & W1-W3

Building

  • Continue Deep Foundation Installation at Office Build-ing: Grid Line OD-OK at O8-O4.

Parking Deck

  • Commence Deep Foundations at Southwest Private Deck: Grid Line P7—P11 & PA.1-PE.7
  • Commence Foundations at Southwest Private Deck: Grid Line P7—P11 & PA.1-PE.7
  • Continue Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PA & P1-P6
  • Complete Shotcrete and Tiebacks at Southwest Private Deck: Gridlines P7—P11 & PA.1-PE.7
  • Continue Shotcrete and Tiebacks at East and West

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE