Construction Activities for the week of January 5, 2017

Construction Activities This Week

Site/Structure

  • Continued Elevator Installation at Precast Deck.
  • Continued Installation of Storm Drainage above CIP Parking Deck.
  • Commenced Excavation for PAC Fountain.

Performing Arts Center

  • Continued Landing Prep of North and South Stairs.
  • Continued Installation of Catwalks and Grating for the Main Trusses at Area C2.
  • Continued Overhead MEP Rough-in at PAC Lower Mechanical Room and Trap Level.
  • Continued Erection of Steel at Follow-Spot/PAC Lobby Roof.
  • Continued Feature Wall Precast Installation.
  • Continued Installation of Brick at North Elevation.
  • Continued Roofing Installation.
  • Continued Installation of Vertical Mullions for Exterior Glass/Glazing at East Elevation.

Office Tower & Studio Theatre

  • Continued SOG Prep at Office Tower Retail Space.
  • Continued Re-shore Removal at Government Level.
  • Continued MEP Overhead Rough-In at Lobby Level.
  • Continued CMU Wall Installation at Service Level.
  • Continued Chiller Plant Piping Installation.
  • Commenced Top Track Installation at Gallery Level.
  • Continued Architectural Precast Installation (Studio Theatre) at North Elevation.
  • Commenced A1 Gallery Misc. Steel Install.
  • Commenced Roof Level Misc. Steel Install.

CIP Deck

  • Continued Installation of Waterproofing at Area F Lid Level.
  • Continued Fire Protection Installation.
  • Continued Equipment Room Pad Layout.
  • Continue Forming of Area D3 Arcade Level.

Roadways

  • Continued Grading of South Parking.
  • Continued Installation of the Storm Structure at South Parking.
  • Continued Demo of Bluestone/Hilderbrand.

Construction Activities Next Week

Site/Structure

  • Continue Elevator Installation at Precast Deck.
  • Continue Installation of Storm Drainage above CIP Parking Deck.

Performing Arts Center

  • Continue Installation of Catwalks and Grating for the Main Trusses at Area C2.
  • Continue Landing Prep of North and South Stairs.
  • Continue Overhead MEP Rough-in at PAC Lower Mechanical Room and Trap Level.
  • Continue Erection of Steel at Follow-Spot/PAC Lobby Roof.
  • Continue MEP Overhead Rough-In at Trap Level.
  • Continue Installation of Vertical Mullions for Exterior Glass/Glazing.
  • Continue Installation of Brick at North Elevation.
  • Continue Roofing Installation.

Office Tower & Studio Theatre

  • Complete Re-shore Removal at Government Level.
  • Complete SOG Installation for Office Tower Retail Space.
  • Continue MEP Overhead Rough-In at Lobby Level.
  • Continue Architectural Precast Installation (Studio Theatre) at North Elevation.
  • Continue CMU Wall Installation at Service Level.
  • Continue Chiller Plant Piping Installation.
  • Continued A1 Gallery Misc. Steel Install.
  • Continued Roof Level Misc. Steel Install.

CIP Deck

  • Continue Fire Protection Installation.
  • Continue Installation of Waterproofing at Area F Lid Level.
  • Continue Equipment Room Pad Layout.
  • Continue Forming of Area D3 Arcade Level.

Roadways

  • Continue Grading of South Parking.
  • Continue Installation of the Storm Structure at South Parking.
  • Continue Roadwork at Bluestone/Hilderbrand.