Construction Activities for the week of January 29, 2016

This Week’s Construction Activities

Site/Structure

  • Completed Tower Crane Installation
  • Continued Site Excavation to Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck

Performing Arts Center

  • Commenced PAC Slab on Grade: Phase 4, Gridlines W1-T5 and WA-WC
  • Commenced PAC Wall Forms and Resteel: Phase 3 & 4, Gridlines WD-TE.5 and TO-Z2
  • Commenced Deep Foundation Installation at PAC: Phase 5, Gridline Y6-W3 & WD-TE.5
  • Continued Wall Forms and Resteel, at PAC: Gridlines W1-W3 & WA-WD

Building

  • Continued Deep Foundation Installation at Office Building: Grid Line OA-OE at O1-O4.

Parking Deck

  • Completed Deep Foundations at Southwest Private Deck: Grid Line P6.2 & PC.5
  • Continued Footings at Southwest Private Deck: Grid-line PA.1-PE.7 & P7-P11
  • Continued Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PN & P5-P7
  • Continued Shotcrete and Tiebacks at East and West Deck: Grid Line PA-PS & P1-P6 and TE-PJJ and Z7-O8

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

 

Next Week’s Construction Activities

Site/Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Commenced PAC Slab on Grade: Phase 4, Gridlines W1-T5 and WA-WC
  • Commenced PAC Wall Forms and Resteel: Phase 3 & 4, Gridlines WD-TE.5 and TO-Z2
  • Commenced Deep Foundation Installation at PAC: Phase 5, Gridline Y6-W3 & WD-TE.5
  • Continued Wall Forms and Resteel, at PAC: Gridlines W1-W3 & WA-WD

Building

  • Continue Deep Foundation Installation at Office Building: Grid Line OB-RA at O1-O4.

Parking Deck

  • Continued Footings at Southwest Private Deck: Grid-line PA.1-PE.7 & P7-P11
  • Continue Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PN & P5-P7
  • Continue Shotcrete and Tiebacks at East and West Deck: Grid Line PH-PS & P1-P6 and TE-PJJ and O8-P6.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE