Construction Activities for the week of January 22, 2016

This Week’s Construction Activities

Site/Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Continue PAC Foundations in Phase 3 & 4: Gridline WD-TE.5 & W1-Z5
  • Completed Underdrain Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3
  • Commenced Under Slab Plumbing and Electrical In-stallation at PAC: Gridline WA-WC & W1-W3
  • Continued Wall Resteel and Form Erecting at PAC: Gridline WA-WC & W1-W3

Building

  • Continued Deep Foundation Installation at Office Building: Grid Line OF-OK at O1-O4.

Parking Deck

  • Continued Deep Foundations at Southwest Private Deck: Grid Line P6.2 & PC.5
  • Commenced Footings at Southwest Private Deck: Gridline PA.1-PE.7 & P9-P11
  • Continued Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PA & P6-P7
  • Completed Tiebacks at Southwest Private Deck: Grid-lines P7—P11 & PA.1-PE.7
  • Continued Shotcrete and Tiebacks at East and West Deck: Grid Line PA-PS & P1-P6 and TE-PJJ and Z7-O8

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

 

Next Week’s Construction Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Commence Deep Foundation Installation at Perform-ing Arts Center: Phase 5, Gridline Y6-W3 & WD-TE.5
  • Commence PAC Foundations in Phase 5: Gridline WA-WC & O5-O8 and WE-TF.7 & Z5-Z7
  • Continue Wall Forms, Resteel, and Installation at PAC: Gridlines W1-W3 & WA-WD

Building

  • Continue Deep Foundation Installation at Office Build-ing: Grid Line OA-OE at O1-O4

Parking Deck

  • Continue Deep Foundations at Southwest Private Deck: Grid Line P6.2 & PC.5
  • Continue Footings at Southwest Private Deck: Gridline PA.1-PE.7 & P7-P11
  • Continue Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PN & P5-P7
  • Continue Tiebacks at West Deck: Gridlines PA-PS at P1
  • Continued Shotcrete and Tiebacks at East and West Deck: Grid Line PA-PS & P1-P6 and TE-PJJ and Z7-O8

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE