Construction Activities for the week of January 15, 2016

This Week’s Construction Activities

Site/Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Completed Brick Mock-Up

Performing Arts Center

  • Completed Deep Foundation Installation at Perform-ing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and Z4-Z6.
  • Continued PAC Foundations in Phase 3 & 4: Gridline WA-WC & O5-O8 and WC-TE.5 & Z1-Z2
  • Commenced Excavation of Phase 5 in Performing Arts Center: Gridline Y6-W3 & WD-TE.5
  • Completed Tower Crane Foundation and Set Pedestal
  • Continued Underdrain Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3
  • Continued Wall Resteel and Form Erecting at PAC: Gridline WA-WC & W1-W3

Building

  • Continued Deep Foundation Installation at Office Building: Grid Line OF-OK at O1-O4.

Parking Deck

  • Commenced Deep Foundations at Southwest Private Deck: Grid Line P11 & PC.5
  • Continued Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PA & P1-P6
  • Completed Tiebacks at Southwest Private Deck: Grid-lines P7—P11 & PA.1-PE.7
  • Continued Shotcrete and Tiebacks at East and West Deck: Grid Line PA-PS & P1-P6 and TE-PJJ and Z7-O8

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

 

Next Week’s Construction Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Commence Deep Foundation Installation at Perform-ing Arts Center: Phase 5, Gridline Y6-W3 & WD-TE.5
  • Continue PAC Foundations in Phase 3 & 4: Gridline WA-WC & O5-O8 and WC-TE.5 & Z1-Z2
  • Continue Underdrain Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3
  • Continue Wall Resteel and Form Erecting at PAC: Grid-line WA-WC & W1-W3

Building

  • Continue Deep Foundation Installation at Office Build-ing: Grid Line OD-OA at O1-O4.

Parking Deck

  • Continue Deep Foundations at Southwest Private Deck: Grid Line P6.2 & PC.5
  • Commence Footings at Southwest Private Deck: Grid-line PA.1-PE.7 & P9-P11
  • Continue Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PA & P6-P7
  • Completed Tiebacks at Southwest Private Deck: Grid-lines P7—P11 & PA.1-PE.7
  • Continued Shotcrete and Tiebacks at East and West Deck: Grid Line PA-PS & P1-P6 and TE-PJJ and Z7-O8

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE