Construction Activities for the week of February 9, 2017

Construction Activities This Week

Site/Structure

  • Completed Pouring of Slip Ramp Walls.
  • Continued Piping Installation for PAC Fountain.
  • Continued Installation of Storm Drainage above CIP Parking Deck.
  • Continued Excavation of Site Walls & Planters at City Green.
  • Commenced Pouring of the Footings for the Site Walls & Planters at City Green.

Performing Arts Center

  • Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.
  • Continued Installation of Brick at North Elevation.
  • Continued Roofing Installation.
  • Continued Installation of Exterior Glass/Glazing at North & East Elevation.
  • Commenced Elevator CE-01 Hoistway Prep.
  • Commenced East Reflector Install at East Flyloft level.
  • Commenced Scaffold Platform Install at Orchestra Seating Level.

Office Tower & Studio Theatre

  • Continued MEP Overhead Rough-In at Lobby Level.
  • Continued CMU Wall Installation at Service Level.
  • Continued Chiller Plant Piping Installation.
  • Continued Roof Level Misc. Steel Install.
  • Continued MEP Overhead Installation at Gallery Level.
  • Continued Installation of Mullions for Glass/Glazing.
  • Continued High Roof Parapet Framing.
  • Continued setting of Cooling Towers & Begin Piping Installation.
  • Continued Elevator Installation at Studio Theatre.

CIP Deck

  • Continued Installation of Arcade Slabs.
  • Continued Pouring of Curbs.
  • Continued Installation of Waterproofing at Area F Lid Level.
  • Continued Fire Protection Installation.
  • Continued Equipment Room Buildout.

Continued Backfill at Area F.

Roadways/Public Utility

  • Completed Paving at Bluestone/Hildebrand.
  • Continued Grading of South Parking.
  • Continued Jack & Bore Operation at Sandy Spring Circle & Johnson Ferry.

Construction Activities Next Week

Site/Structure

  • Commence Pouring of the Lower Basin for the PAC Fountain.
  • Continue Pouring of the Footings for the Site Walls & Planters at City Green.
  • Continue Excavation of Site Walls & Planters at City Green.
  • Continue Elevator Installation at Precast Deck.
  • Continue Installation of Storm Drainage above CIP Parking Deck.

Performing Arts Center

  • Continue Landing Prep of North and South Stairs.
  • Continue Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.
  • Continue Erection of Steel at Follow-Spot/PAC Lobby Roof.
  • Continue Installation of Exterior Glass/Glazing at North & East Elevation.
  • Continue Installation of Brick at North Elevation.
  • Continue Roofing Installation.
  • Continue Elevator CE-01 Hoistway Prep.
  • Continue East Reflector Install at East Flyloft Level.

Office Tower & Studio Theatre

  • Continue MEP Overhead Rough-In at Conference & Gallery Level.
  • Continue CMU Wall Installation at Service Level.
  • Continue Chiller Plant Piping Installation.
  • Continue Roof Level Misc. Steel Install.
  • Continue Top Track Installation at Conference Level.
  • Continue Glass/Glazing Prep Work.
  • Continue High Roof Parapet Framing.
  • Continue Elevator Installation at Studio Theatre.
  • Continue Cooling Tower Piping Installation.
  • Commence Framing at Gallery Level.

CIP Deck

  • Complete Installation of Slip Ramp Walls.
  • Continue Fire Protection Installation.
  • Continue Installation of Waterproofing at Area F Lid Level.
  • Continue Equipment Room Buildout.

Roadways/Utilities

  • Complete Paving at Bluestone/Hildebrand.
  • Continue Grading of South Parking.
  • Continue Jack & Bore Operation at Sandy Spring Circle & Johnson Ferry.