Construction Activities for the week of February 26, 2016

Precast material deliveries for the parking deck began arriving this week. Trucks will stage off-site with deliveries made “just in time” to limit road disturbance. Please watch for the flagmen as those deliveries are made.

 

This Week’s Construction Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Continued Excavation & Pouring of Footing: Along O8 line.
  • Continued Forming and Installation of Resteel: Along YB and WR line.
  • Continued Gravel Back Fill & Installation of Water-proofing Along WA Line.

Building

  • Continued Deep Foundation Installation at Office.
  • Continued Excavation of O8 Line.

Parking Deck

  • Commenced Column Installation at Southwest Cast-In Place Deck: Gridline PA-PG Line All Footings.
  • Continued Additional Deep Foundation Drilled Piers: Gridline PCC-PJJ Line
  • Continued Shotcrete and Tiebacks at East and West Deck: Grid Line: PCC—PJJ.
  • Commenced Erection of Precast Panels for Southwest Private Deck.
  • Completed Under Drain Installation at Southwest Private Deck: Gridlines P7– P11.
  • Western Sump Pit Installation Completed.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.
  • Dirt Stockpile in at NW Corner of Site ongoing.

 

Next Week’s Construction Activities

Site/Structure

  • Continue Site Excavation to Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Complete PAC Seating Area SOG Prep and Pour.
  • Complete Slab on Grade Installation at Stage Front.
  • Continue Gravel Back Fill & Installation of Waterproofing Along WA Line.
  • Complete Foundation Installation in Area C2: Grid Lines WC-TE.5.

Building

  • Continue Deep Foundation Installation at Office.
  • Continue Excavation of O8 Line.
  • Commence Footing prep and pour in Area B1.

Parking Deck

  • Continue Column Installation at Southwest Cast-In-Place Deck: Gridline PA-PG Line All Footings.
  • Continue Additional Deep Foundation Drilled Piers: Gridline PCC-PJJ Line
  • Continue (2nd Lift) Shotcrete and Tiebacks at East and West Deck: Grid Line: PCC—PJJ.
  • Continue Erection of Precast Panels for Southwest Private Deck.
  • Commence Slab on Grade Installation in Southwest Private Deck: Gridlines P7-P8.
  • Commence Slab of Grade prep: Grid Lines PA-PF.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE
  • Complete Dirt Stockpile in at NW Corner of Site.