Construction Activities for the week of February 2, 2017

Construction Activities This Week

Site/Structure

Continued Elevator Installation at Precast Deck.

Continued Piping Installation for PAC Fountain.

Continued Installation of Storm Drainage above CIP Parking Deck.

Continued Pouring of Slip Ramp Walls.

Continued Excavation of Site Walls & Planters at City Green.

Performing Arts Center

Continued Catwalk and Handrail Backwelding for the Flyloft at Area C2.

Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.

Continued Installation of Brick at North Elevation.

Continued Roofing Installation.

Continued Installation of Exterior Glass/Glazing at North & East Elevation.

Office Tower & Studio Theatre

Completed Architectural Precast Installation (Studio Theatre) at South Elevation.

Continued MEP Overhead Rough-In at Lobby Level.

Continued CMU Wall Installation at Service Level.

Continued Chiller Plant Piping Installation.

Continued Roof Level Misc. Steel Install.

Continued MEP Overhead Installation at Gallery Level.

Continued Installation of Mullions for Glass/Glazing.

Continued High Roof Parapet Framing.

CIP Deck

Continued Installation of Waterproofing at Area F Lid Level.

Continued Fire Protection Installation.

Continued Equipment Room Buildout.

Continued Pouring Arcade Slabs.

Commenced Backfill at Area F.

Commenced Elevator Installation at Studio Theatre.

Roadways

Completed Installation of Curb & Gutter at Bluestone/ Hilderbrand.

Commenced Paving at Bluestone/Hildebrand.

Continued Grading of South Parking.

Commenced Jack & Bore Operation at Sandy Springs Circle & Johnson Ferry.

Construction Activities Next Week

Site/Structure

Commence Pouring of the Lower Basin for the PAC Fountain.

Commence Pouring of the Footings for the Site Walls & Planters at City Green.

Continue Elevator Installation at Precast Deck.

Continue Installation of Storm Drainage above CIP Parking Deck.

Continue Pouring of Slip Ramp Walls.

Performing Arts Center

Continue Catwalk and Handrail Backwelding for the Flyloft at Area C2.

Continue Landing Prep of North and South Stairs.

Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.

Continue Erection of Steel at Follow-Spot/PAC Lobby Roof.

Continue Installation of Exterior Glass/Glazing at

North & East Elevation.

Continue Installation of Brick at North Elevation.

Continue Roofing Installation.

Office Tower & Studio Theatre

Continue MEP Overhead Rough-In at Conference & Gallery Level.

Continue CMU Wall Installation at Service Level.

Continue Chiller Plant Piping Installation.

Continue Roof Level Misc. Steel Install.

Continue Top Track Installation at Conference Level.

Continue Glass/Glazing Prep Work.

Continue High Roof Parapet Framing.

Continue Elevator Installation at Studio Theatre.

Set Cooling Towers & Begin Piping Installation.

CIP Deck

Continue Fire Protection Installation.

Continue Installation of Waterproofing at Area F Lid Level.

Continue Equipment Room Buildout.

Complete Pouring Arcade Slab.

Roadways

Complete Paving at Bluestone/Hildebrand.

Continue Grading of South Parking.

Continue Jack & Bore Operation at Sandy Spring Circle & Johnson Ferry.