Construction Activities for the week of February 19, 2016

This Week’s Construction Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck

Performing Arts Center

  • Commenced Excavation & Pouring of Footing: Along O8
  • Commenced Vertical Wall, Resteel, and Placement:
  • Along YB and WR
  • Continued Gravel Back Fill & Installation of Water- proofing Along North Wall: W1
  • Commenced Elevated Slab Pour: Stage

Building

  • Continued Deep Foundation Installation at
  • Continued Excavation of O8 Line

Parking Deck

  • Completed Footings at Southwest Private Deck: Grid- lines P7-P11.
  • Completed Footings at Southwest Cast-In-Place Deck:
  • Gridline PA-PG Line All
  • Commence Additional Deep Foundation Drilled Piers: Gridline PCC-PJJ Line
  • Continue Controlled Rock Blasting in Cast-In-Place
  • Parking Deck: Grid Line PCC-PJJ Zone
  • Continue Shotcrete and Tiebacks at East and West Deck: Grid Line: PCC—PJJ.
  • Mobilize Precast Erection Crane for Southwest Private
  • Deck
  • Commence Under Drain Installation: Gridlines P7-P11.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE
  • Dirt Stockpile in at NW Corner of Site ongoing.

 

Next Week’s Construction Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East

Performing Arts Center

  • Continue Excavation & Pouring of Footing: Along O8 line.
  • Continue Forming and Installation of Resteel: Along YB and WR
  • Continue Gravel Back Fill & Installation of Waterproof- ing Along WA

Building

  • Continue Deep Foundation Installation at
  • Continue Excavation of O8 Line

Building

  • Continue Deep Foundation Installation at Office.
  • Continue Excavation of O8 Line

Parking Deck

  • Commence Column Installation at Southwest Cast-In- Place Deck: Gridline PA-PG Line All
  • Continue Additional Deep Foundation Drilled Piers: Gridline PCC-PJJ Line
  • Continue Shotcrete and Tiebacks at East and West Deck: Grid Line: PCC—PJJ.
  • Commence Erection of Precast Panels for Southwest Private
  • Continue Under Drain Installation at Southwest Private Deck: Gridlines P7–
  • Commence Slab on Grade Installation in Southwest Private Deck: Gridlines P7-P8.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE
  • Complete Dirt Stockpile in at NW Corner of site