Construction Activities for the week of February 12, 2016

This Week’s Construction Activities

Site/Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck

Performing Arts Center

  • Commenced Waterproofing on North Wall: Grid Line W1.
  • Completed Slab on Grade Prep and Placement: Phase 4, Gridlines W1-W3 & WA-WD.
  • Commenced 2nd Lift Wall Forms and Placement: Phase 4, W1-W3 & WA-WD.
  • Continue Spread Footing and Grade Beam Excavation, Resteel, and Placement: Gridline Wd-Te.5 &X1-Y7.
  • Commenced Waterproofing & Back Fill on North Wall: W1 Line.
  • Completed Drilled Piers: 80A, 80B, and 83

Building

  • Continued Deep Foundation Installation at Office Building: Grid Line R1-R2 Line.
  • Continued O8 Grid Line Excavation

Parking Deck

  • Continued Footings at Southwest Private Deck: Grid-lines P7-P11.
  • Installed Footings along Grid Line: P6.
  • Continued Controlled Rock Blasting in CIP Parking Deck: 8-P2.4 & PG-PH
  • Continue Shotcrete and Tiebacks at East and West Deck: Grid Line PH-PS & P1-P6 and TE-PJJ and O8-P6

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE
  • Completed Existing Wall Demo at Mount Vernon HWY NE
  • Dirt Stockpile in at NW Corner of Site ongoing.

 

Next Week’s Construction Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Commence Excavation & Pouring of Footing: Along O8 line.
  • Forming Vertical Wall, Resteel, and Placement: Grid-line O8 between TC—TA
  • Continue Gravel Back Fill & Installation of Waterproofing Along North Wall: W1 line.

Building

  • Continue Deep Foundation Installation at Office.
  • Continue Excavation of O8 Line

Parking Deck

  • Continue Footings at Southwest Private Deck: Gridline PA-PG Line All Footings.
  • Commence Additional Deep Foundation Drilled Piers: Gridline PCC-PJJ Line
  • Continue Controlled Rock Blasting in CIP Parking Deck: Grid Line PCC-PJJ Zone
  • Continue Shotcrete and Tiebacks at East and West Deck: Grid Line: PCC—PJJ.
  • Mobilize Precast Erection Crane.
  • Commence Under Drain Installation.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE
  • Complete Dirt Stockpile in at NW Corner of Site.