Construction Activities for the Week of December 4, 2015

Activities This Week

Site/Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continued H-Pile Installation in East Deck with Kelly Bar: Section 4, Grid Lines PW to PBB at P6
  • Continued Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 4, Grid Line WA—WC and T5-W3 and Phase 2, Grid Line TB.4 to TC.5 at TO
  • Continued Deep Foundation Installation at Office Building: Grid Line PQ-PS & R6-R8.
  • Continued Shotcrete at Southwest Private Deck, West Deck, and East Deck: Grid Line P7—P11 & PA.1-PE.7, PH-PS at P1/ PE-PS at P6, and T7-08 at TE.
  • Continued Shotcrete Prep in Southwest Private Deck, West Deck, and East Deck : Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6, and T7-08 at TE.
  • Completed Tie-Backs at West Deck and East Deck Shoring Walls: Grid Line PG-PH & P1-P0.1, and T7-08 at TE.
  • Began Row 2 Tie-Backs at Southwest Private Deck Shoring Walls: Grid Line P7—P11 & PA.1-PE.7.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

Next Week’s Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue H-Pile Installation in East Deck with Kelly Bar: Section 3, Grid Lines PFF- PJJ and P4-P6
  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and TO-Z2.
  • Continue Deep Foundation Installation at Office Build-ing: Grid Line PQ-PS & R6-R8.
  • Continue Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Continue Shotcrete Prep in Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Complete Row 2 Tie-Backs at Southwest Private Deck Shoring Walls: Grid Line P7—P11 & PA.1-PE.7.
  • Begin Row 2 Tie-Backs at West Deck: Grid Line PA-PP & P1-P6.
  • Commence PAC Foundations and Underdrain System: Gridline WA-WC & W1– T2

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE