Construction Activity This Week

Site/Structure

  • Completed Slip Ramp SOG Installation.
  • Continued Elevator Installation at Precast Deck.
  • Continued Installation of Storm Drainage above CIP Parking Deck.
  • Commenced moving of trailers to South Parking.

Performing Arts Center

  • Completed Installation of Decking at Area C5.
  • Completed Installation of Architectural Precast at South elevation.
  • Continued Landing Prep of North and South Stairs.
  • Continued Installation of Catwalks and Grating for the Main Trusses at Area C2.
  • Continued Overhead MEP Rough-in at PAC Lower Mechanical Room and Trap Level.
  • Continued Erection of Steel at Follow-Spot/PAC Lobby Roof.
  • Continued Feature Wall Precast Installation.
  • Continued Installation of Brick at North Elevation.
  • Commenced Roofing Installation.
  • Commenced Installation of Vertical Mullions for Exterior Glass/Glazing at East Elevation.

Office Tower & Studio Theatre

  • Continued SOG Installation at Office Tower Retail Space.
  • Completed Final Pour of Office Tower at A1/A2 Penthouse Roof Level.
  • Continued Re-shore Removal at Government Level.
  • Continued MEP Overhead Rough-In at Lobby Level.
  • Continue CMU Wall Installation at Service Level.

CIP Deck

  • Completed Installation of Waterproofing at Area E Lid Level.
  • Continued Installation of Waterproofing at Area F Lid Level.
  • Continued Fire Protection Installation.

Roadways

  • Continued Grading of South Parking.
  • Continued Installation of the Storm Structure at South Parking.
  • Continued Demo of Bluestone/Hilderbrand.

Construction Activity Next Week

Site/Structure

  • Complete Moving of trailers to South Parking.
  • Continue Elevator Installation at Precast Deck.
  • Continue Installation of Storm Drainage above CIP Parking Deck.

Performing Arts Center

  • Continue Installation of Catwalks and Grating for the Main Trusses at Area C2.
  • Continue Landing Prep of North and South Stairs.
  • Continue Overhead MEP Rough-in at PAC Lower Mechanical Room and Trap Level.
  • Continue Erection of Steel at Follow-Spot/PAC Lobby Roof.
  • Continue MEP Overhead Rough-In at Trap Level.
  • Continue Installation of Vertical Mullions for Exterior Glass/Glazing.
  • Continue Installation of Brick at North Elevation.
  • Continue Roofing Installation.
  • Commence Fire Protection Installation.

Office Tower & Studio Theatre

  • Continue Re-shore Removal at Tenant & Government Level.
  • Continue SOG Installation for Office Tower Retail Space.
  • Continue MEP Overhead Rough-In at Lobby Level.
  • Commence Architectural Precast Installation (Studio Theatre) at North Elevation.
  • Continue CMU Wall Installation at Service Level.
  • Continue Chiller Plant Piping.

CIP Deck

  • Continue Fire Protection Installation.
  • Continue Installation of Waterproofing at Area F Lid Level.
  • Continue Forming of Area D3 Arcade Level.

Roadways

  • Continue Grading of South Parking.
  • Continue Installation of the Storm Structure at South Parking.
  • Continue Demo of Bluestone/Hilderbrand.