ACTIVITIES THIS WEEK:

Site / Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continued Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and TO-Z2.
  • Completed Deep Foundation Installation at Office Building: Grid Line PQ-PS & R6-R8.
  • »Continued Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Continued Shotcrete Prep in Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Continued Row 2 Tie-Backs at West Deck: Grid Line PA-PP & P1-P6.
  • Commenced Controlled Rock Blasting in CIP Parking Deck
  • Continued PAC Foundations and Underdrain System: Gridline WA-WC & T5-W3
  • Commenced PAC Foundation Pour: Gridline WA-WC & W1-W3
  • Commenced Drainage Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

 

ACTIVITIES NEXT WEEK

Site / Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and Z4-Z6.
  • Continue PAC Foundations: Gridline WA-WC & O5-O8
  • Continue Underdrain Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3
  • Commence Wall Resteel and Form Erecting at PAC: Gridline WA-WC & W1-W3

Building

  • Continue Deep Foundation Installation at Office Build-ing: Grid Line P2-PV at O6.

Parking Deck

  • Continue Controlled Rock Blasting in CIP Parking Deck: Grid Line PS-PK & P1-P6
  • Continue Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Continue Shotcrete Prep in Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Complete Row 2 Tie-Backs at West Deck: Grid Line PA -PP & P1-P6.
  • Commence Row 3 Tie-Backs at SWP Deck: Grid Line P7—P11 & PA.1-PE.7

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE