Construction Activities for the week of December 15, 2016

Construction Activities This Week

Site/Structure

  • Complete Installation of LS/HS Mockup on Bluestone.
  • Continued Grading for SOG at Office Tower.
  • Continued Elevator Installation at Precast Deck.
  • Commenced Installation of Storm Drainage above CIP Parking Deck.
  • Commenced Slip Ramp Foundation/SOG Installation.

Performing Arts Center

  • Completed Installation of PAC Area C1 & C2 Roof.
  • Completed Installation of Decking at Area C5.
  • Continued Landing Prep of North and South Stairs.
  • Continued Installation of Catwalks and Grating for the Main Trusses at Area C2.
  • Continued Overhead MEP Rough-in at PAC Lower Mechanical Room.
  • Continued Installation of Architectural Precast at South Elevation.
  • Commenced Erection of Steel at Follow-Spot/PAC Lobby Roof.
  • Commenced Feature Wall Precast Installation.

Office Tower & Studio Theatre

  • Completed SOG Installation of Loading Dock at Service Level Area A.
  • Completed Layout & Top Track in Studio Theatre for Wall Framing.
  • Completed Installation of Generators at the Service Level.
  • Completed Installation of A3/A4 Roof Level.
  • Continued Re-shore Removal at A1 Conference Level.
  • Commenced Forming & Reinforcing of Area A1/A2 Penthouse Roof Level.
  • Commenced MEP Overhead Rough-In at Lobby Level.

CIP Deck

  • Completed Final Lid Pour at Area F1.
  • Continued Fire Protection Installation.
  • Continued Installation of Waterproofing at Area E Lid Level.

Roadways

  • Continued Grading of South Parking.
  • Continued Installation of the Storm Structure at South Parking.
  • Commenced Demo of Bluestone/Hilderbrand.

Construction Activities Next Week

Site/Structure

  • Continue Grading for SOG at Office Tower.
  • Continue Elevator Installation at Precast Deck.
  • Continue Installation of Storm Drainage above CIP Parking Deck.
  • Continue Slip Ramp Foundation/SOG Installation.

Performing Arts Center

  • Continue Installation of Catwalks and Grating for the Main Trusses at Area C2.
  • Continue Landing Prep of North and South Stairs.
  • Continue Overhead MEP Rough-in at PAC Lower Mechanical Room.
  • Continue Installation of Architectural Precast at South Elevation.
  • Continue Erection of Steel at Follow-Spot/PAC Lobby Roof.
  • Continue Feature Wall Precast Installation.

Office Tower & Studio Theatre

  • Complete Re-shore Removal at A1 Conference & Gallery Level.
  • Complete Installation of Final Elevated Slab—Area A1/A2 Penthouse Roof Level.
  • Complete Installation of Loading Dock Ramp at Service Level Area A.
  • Complete SOG Installation of Kitchen at Service Level Area A.
  • Continue MEP Overhead Rough-In at Lobby Level.
  • Commence Re-shore Removal at A2 Conference Level.
  • Commence Architectural Precast Installation at North Elevation.

CIP Deck

  • Continue Fire Protection Installation.
  • Continue Installation of Waterproofing at Area E Lid Level.
  • Commence Installation of Waterproofing at Area F Lid Level.
  • Commence Forming of Area D3 Arcade Level.

Roadways

  • Continue Grading of South Parking.
  • Continue Installation of the Storm Structure at South Parking.