Construction Activities for the Week of December 11, 2015

THIS WEEK’S ACTIVITIES

We began pouring concrete at the site of the performing arts center this week, a noteworthy milestone.  The construction team created this video to demonstrate their ‘order of operations.’

Site/Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Completed H-Pile Installation in East Deck with Kelly Bar: Section 3, Grid Lines PFF- PJJ and P4-P6
  • Continued Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and TO-Z2.
  • Continued Deep Foundation Installation at Office Building: Grid Line PQ-PS & R5-R8.
  • Continued Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Continued Shotcrete Prep in Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Completed Row 2 Tie-Backs at Southwest Private Deck Shoring Walls: Grid Line P7—P11 & PA.1-PE.7.
  • Commenced Row 2 Tie-Backs at West Deck: Grid Line PA-PP & P1-P7
  • Commenced PAC Foundations and Underdrain Sys-tem: Gridline WA-WC & W1– T5

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

 

NEXT WEEK’S ACTIVITIES

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and TO-Z2.
  • Complete Deep Foundation Installation at Office Building: Grid Line PQ-PS & R6-R8.
  • Continue Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Continue Shotcrete Prep in Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Continue Row 2 Tie-Backs at West Deck: Grid Line PA -PP & P1-P6.
  • Commence Controlled Rock Blasting in CIP Parking Deck
  • Continue PAC Foundations and Underdrain System: Gridline WA-WC & T5-W3
  • Commence PAC Foundation Pour: Gridline WA-WC & W1-W3
  • Commence Drainage Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE