THIS WEEK’S ACTIVITIES
We began pouring concrete at the site of the performing arts center this week, a noteworthy milestone. The construction team created this video to demonstrate their ‘order of operations.’
Site/Structure
- Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
- Completed H-Pile Installation in East Deck with Kelly Bar: Section 3, Grid Lines PFF- PJJ and P4-P6
- Continued Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and TO-Z2.
- Continued Deep Foundation Installation at Office Building: Grid Line PQ-PS & R5-R8.
- Continued Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
- Continued Shotcrete Prep in Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
- Completed Row 2 Tie-Backs at Southwest Private Deck Shoring Walls: Grid Line P7—P11 & PA.1-PE.7.
- Commenced Row 2 Tie-Backs at West Deck: Grid Line PA-PP & P1-P7
- Commenced PAC Foundations and Underdrain Sys-tem: Gridline WA-WC & W1– T5
Other
- Continue Georgia Power Trenching at Mount Vernon HWY NE
NEXT WEEK’S ACTIVITIES
Site/Structure
- Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
- Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and TO-Z2.
- Complete Deep Foundation Installation at Office Building: Grid Line PQ-PS & R6-R8.
- Continue Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
- Continue Shotcrete Prep in Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
- Continue Row 2 Tie-Backs at West Deck: Grid Line PA -PP & P1-P6.
- Commence Controlled Rock Blasting in CIP Parking Deck
- Continue PAC Foundations and Underdrain System: Gridline WA-WC & T5-W3
- Commence PAC Foundation Pour: Gridline WA-WC & W1-W3
- Commence Drainage Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3
Other
- Continue Georgia Power Trenching at Mount Vernon HWY NE