Construction Activities for the week of December 1, 2016

Construction Activities This Week

Site/Structure

  • Completed Interior Waterproofing of the Irrigation Cistern.
  • Completed Slip Ramp Excavation and Shoring Wall Installation.
  • Continued Grading for SOG at Office Tower.
  • Continued Elevator Installation at Precast Deck.

Performing Arts Center

  • Completed Architectural Precast Installation at the West Elevation.
  • Continued Landing Prep of North and South Stairs.
  • Continued Installation of Catwalks and Grating for the Main Trusses at Area C2.
  • Continued Overhead MEP Rough-in at PAC Lower Mechanical Room.
  • Continued Erection of Structural Steel at Area C5.
  • Commenced Architectural Precast Installation at the East Elevation High Roof.

Office Tower & Studio Theatre

  • Completed Installation of A1 Government Roof.
  • Completed Installation of Mechanical Room at Area A Service Level.
  • Continued Re-shore Removal at A1 Conference Level.
  • Continued SOG Prep for Loading Dock at Service Level Area A.
  • Continued Layout & Top Track in Studio Theatre for Wall Framing.

CIP Deck

  • Completed Installation of Area F3 Lid Level.
  • Continued Fire Protection Installation.
  • Commenced Installation of Waterproofing at Area E Lid Level.
  • Continued Forming & Reinforcing of Area F1 & F2 Lid Level.

Roadways

  • Continued Grading of South Parking.
  • Continued Installation of the Storm Structure at South Parking

Other

  • Continued Georgia Power Trenching at Roswell Road.

Construction Activities Next Week

Site/Structure

  • Continue Grading for SOG at Office Tower.
  • Continue Elevator Installation at Precast Deck.
  • Commence Slip Ramp Foundation/SOG Installation.

Performing Arts Center

  • Complete Installation of C2 Roof.
  • Continue Landing Prep of North and South Stairs.
  • Continue Installation of Catwalks and Grating for the Main Trusses at Area C2.
  • Continue Overhead MEP Rough-in at PAC Lower Mechanical Room.
  • Complete Erection of Structural Steel at Area C5.
  • Commence Installation of Architectural Precast at South Elevation.

Office Tower & Studio Theatre

  • Complete Installation of A2 Government Roof.
  • Continue Re-shore Removal at A1 Conference Level.
  • Continue SOG Prep for Loading Dock at Service Level Area A.
  • Continue Layout & Top Track in Studio Theatre for Wall Framing.
  • Commence Forming & Reinforcing of Area A3 Roof Level.

CIP Deck

  • Complete Installation of Area F2 Lid Level.
  • Continue Fire Protection Installation.
  • Continue Installation of Waterproofing at Area E Lid Level.
  • Continue Forming & Reinforcing of Area F1 Lid Level.

Roadways

  • Continue Grading of South Parking.

Other

  • Continue Georgia Power Trenching at Roswell Road
  • Commence Georgia Power Jack & Bore Operation at Roswell Road