Construction Activities for the week of August 18, 2016

Construction Activities This Week

Site/Structure

  • Completed Underground Storm, Water and Fire line Installation South of Area G.
  • Completed Underground Duct Bank Installation South of Area G.
  • Continued Installation of Grease traps at the Fidelity Bank Site.
  • Completed Final Grading for the South Parcel Turnover to Brassfield & Gorrie.

Performing Arts Center

  • Completed 1st & 2nd lift of the PAC Stage.
  • Completed Second Lift of the Proscenium Wall.
  • Poured South Balcony.
  • Continue Forming C6 Roof.

Office Tower

  • Continued Installation of Continuous Footings & Columns at Office Tower at Area A.
  • Continued to Form and Reinforce A1 & A2 Lobby Level.
  • Pour A1 Lobby Level.

CIP Parking Deck

  • Completed backfill of the Planter Depressions at Area G.
  • Completed Column Installation at Area D.
  • Continued Column & Footing Installation at E.
  • Continued Dirt Ramp removal in to CIP Deck.
  • Pour Slab on Grade Prep at Area D.

Roadways

  • Completed placement of GAB for Pedestrian Site Access.
  • Complete temporary striping at the intersection of Sandy Springs Circle & Mt. Vernon Hwy.
  • Continued Curb & Gutter Installation for Mt. Vernon and Bluestone Rd.
  • Continued Grading along Mt. Vernon Hwy.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE and Roswell Road.

Construction Activities Next Week

Site/Structure

  • Complete Dirt Ramp removal in to CIP Deck.
  • Complete Market Square Storm Drainage Installation.
  • Complete Installation of Grease traps at the Fidelity Bank Site.
  • Commence Under Slab drainage at Area E.
  • Commence Southwest Retaining Wall Construction.

Performing Arts Center

  • Complete Installation of the Proscenium Walls.
  • Continue WA Wall Installation—West Stage.
  • Continue forming/topping out of the Northeast Walls.
  • Continue forming C6 Roof.

Office Tower

  • Complete Installation of Continuous Footings and Columns at Office Tower.
  • Complete Installation of A2 Lobby Level.
  • Continue Forming and Reinforcing of A3 Lobby Level.

CIP Parking Deck

  • Continue Fire Protection Installation.
  • Continue Forming and Reinforcing of Area D1.
  • Continue Area E Column and Footing Installation.

Roadways

  • Complete pressure test of 16” and 12” Water Main along Mt. Vernon Hwy.
  • Continue Underground Utility work on Mt. Vernon working East.
  • Commence Paving Along Mt. Vernon Hwy & Bluestone Rd.
  • Shift Site Access to Mt. Vernon Hwy East Entrance.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE and Roswell Road