Construction Activities for the week of August 11, 2016

This Week’s Construction Activities

Site/Structure

  • Completed Under Slab Drainage at Area D.
  • Continued Installation of Grease traps at the Fidelity Bank Site.
  • Continued Backfill of the lid at Area G.
  • Continued Underground Storm, Water and Fire line Installation South of Area G.
  • Continued Underground Duct Bank Installation South of Area G.

Performing Arts Center

  • Continued forming/topping out of the Northeast Walls.
  • Continued Re-Steel installation on WA Wall—West Stage.
  • Poured first lift of the Proscenium Wall; continue to form and reinforce the second lift.

Office Tower

  • Completed Installation of Foundations and Pits at Elevators AE01,AE02,AE03 & AE04.
  • Continued Installation of Continuous Footings & Columns at Office Tower at Area A.
  • Continued Forming of A1 Lobby Level.

CIP Parking Deck

  • Commenced backfill of the Planter Depressions at Area G.
  • Continued Column Installation at Area D & E.
  • Continued Footing Installation at E.
  • Continued Slab on Grade Prep at Area D.
  • Began Dirt Ramp removal in to CIP Deck.

Precast Parking Deck

  • Completed Roofing Installation.
  • Completed Fire Protection Installation.
  • Completed Installation of Elevator Structural Steel for the West Elevator.

Roadways

  • Completed Phase 1 of Curb & Gutter Installation for Mt. Vernon and Bluestone Rd.
  • Completed placement of GAB at Bluestone Rd.
  • Shift Main Entrance to Hilderbrand via Bluestone Rd.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.
  • Commenced Trenching at Roswell Road.

Next Week’s Construction Activities

Site/Structure

  • Commence Under Slab drainage at Area E.
  • Complete Underground Storm Line Installation South of Area G.
  • Complete Underground Duct Bank Installation South of Area G.
  • Complete Backfill of Lid at Area G.
  • Complete Installation of Grease traps at the Fidelity Bank Site.

Performing Arts Center

  • Continue WA Wall Installation—West Stage.
  • Continue prepping for the next lift of the Proscenium Wall.
  • Continue forming/topping out of the Northeast Walls.
  • Pour South Grid Iron Beams.

Office Tower

  • Complete Installation of A1 Lobby Level.
  • Continue Forming of A2 Lobby Level.
  • Continue Installation of Continuous Footings & Columns at Office Tower.

CIP Parking Deck

  • Commence Fire Protection Installation.
  • Complete Installation of SOG at Area D.
  • Continue Vertical Wall & Column Installation at Area D.
  • Continue Area E Footing Installation.

Precast Parking Deck

  • Commence Elevator Steel Installation for East Elevator.

Roadways

  • Continue Underground Utility work on Mt. Vernon working East.
  • Continue Grading along Mt. Vernon—Continuing East.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE.
  • Continue Trenching at Roswell Road.