Construction Activities for the week of April 20, 2017

Construction Activities This Week

Site/Park

  • Completed Forming of Planters, Site Walls & Stair at the City Green.
  • Continued Forming of Plaza & Interactive Fountain.
  • Continued Forming of the Waterwall Fountain.
  • Continued Waterproofing of the PAC Fountain.
  • Commenced Forming of Planters, Site Walls & Stair at the Shade Bosque.

Performing Arts Center

  • Continued hanging Hard Ceilings at East Balcony.
  • Continued PAC Scaffolding at Orchestra Level.
  • Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.
  • Continued Fire Protection Installation at Gallery Level and Lobby Bar.
  • Continued Plaster Installation.
  • Continued CE-01 Elevator Installation.
  • Continued MEP Overhead Installation at Lobby Level.
  • Continued Brick Installation at North Elevation.

Office Tower & Studio Theatre

  • Continued Framing at Government Level.
  • Continued CMU Wall Installation at Retail Space.
  • Continue Stair Installation.
  • Continued Chiller Plant Piping Installation.
  • Continued MEP Overhead Installation at Govt. Level.
  • Continued Installation of Glass/Glazing.
  • Continued Elevator Installation at Studio Theatre.
  • Continued Roofing Installation at Office Tower.
  • Continued Drywall Installation at Studio Theatre.
  • Continued Installation of Hoods at Kitchen.

CIP Deck

  • Continued Fire Protection Installation.
  • Continued Equipment Room Buildout.
  • Continued Pre-testing of All Life Safety Equipment.

Roadways/Public Utility

  • Completed Sanitary Sewer work at Sandy Springs East.
  • Continued Curb & Gutter Install at Sandy Springs East.
  • Commence C1 to C2 Storm Tie-in.

Construction Activities Next Week

Site/Park

  • Continue Forming of Plaza & Interactive Fountain.
  • Continue Forming of the Waterwall Fountain.
  • Continue Waterproofing of the PAC Fountain.
  • Commence Forming of Planters, Site Walls & Stair at the Shade Bosque.

Performing Arts Center

  • Continue hanging Hard Ceilings at East Balcony.
  • Continue PAC Scaffolding at Orchestra Level.
  • Continue Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.
  • Continue Fire Protection Installation at Gallery Level and Lobby Bar.
  • Continue Plaster Installation.
  • Continue CE-01 Elevator Installation.
  • Continue MEP Overhead Installation at Lobby Level.
  • Continue Brick Installation at North Elevation.

Office Tower & Studio Theatre

  • Continue Framing at Government Level.
  • Continue CMU Wall Installation at Retail Space.
  • Continue Stair Installation.
  • Continue MEP Overhead Installation at Govt. Level.
  • Continue Installation of Glass/Glazing.
  • Continue Roofing Installation at Office Tower.
  • Continue Drywall Installation at Studio Theatre.
  • Continue Installation of Hoods at Kitchen.

CIP Deck

  • Continue Fire Protection Installation.
  • Continue Equipment Room Buildout.
  • Continue Pre-testing of All Life Safety Equipment.

Roadways/Utilities

  • Continue Curb & Gutter Install at Sandy Springs East.
  • Continue C1 to C2 Storm Tie-in.