Construction Activities for the week ending March 25, 2016

This Week’s Construction Activities

Site/Structure

  • Complete Site Excavation to Grade in at Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place Deck.

Performing Arts Center

  • Continued North PAC Foundations: Area C5.
  • Continued Gravel Back Fill & Installation of Water-proofing at Studio Theatre.
  • Continued PAC Stage Wall 2nd Vertical lift.
  • Began Studio Theatre Foundation Pier Caps.
  • Complete Orchestra Seating Slab Formwork & Rein-forcing.

Building

  • Began Excavation Below Grade Elevator Pits.
  • Continued Backfill of O8 Line.
  • Continued Below Grade Pier Caps in Area B1.

Parking Deck

  • Continued Column & Shear Wall Installation at Area F Cast-In-Place Deck: All Foundations progressing East.
  • Continued additional Deep Foundation Drilled Piers: East Side of Cast-In-Place Deck.
  • Completed Shotcrete and Tiebacks at East Deck: (4th Lift)
  • Completed Erection of Precast Panels for Southwest Private Deck: Sequence 2.
  • Began Sequence 3 for Precast Panel for Southwest Private Deck installation.
  • Completed Slab on Grade Pour: Area G
  • Began Slab on Grade Prep: Area F & Underground MEP.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.
  • Completed Reseed & Hay cover of Northwest Stock Pile.

 

Next Week’s Construction Activities

Site/Structure

  • Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place Deck

Performing Arts Center

  • Continue North PAC Foundations: Area C5.
  • Continue 2nd lift of Area C1 Arbor Pit Walls.
  • Continue Gravel Back Fill & Installation of Waterproofing along Studio Theater East Wall.
  • Complete PAC Stage Wall 2nd Vertical lift.
  • Continue Studio Theater Foundations.
  • Complete Orchestra Seating Slab.

Building

  • Continue Backfill of O8 Line.
  • Continue Continuous Footings at Office Tower.
  • Continue Excavation of Below Grade Elevator Pits.
  • Continue Below Grade Pier Cap Installation.

Parking Deck

  • Continue Column & Shear Wall Installation at Area F Cast-In-Place Deck: All Foundations progressing East.
  • Complete additional Deep Foundation Drilled Piers: South of PAC in CIP Deck East Side.
  • Begin Shotcrete and Tiebacks at East Deck: Final Lift.
  • Continue Erection of Precast Panels for Southwest Private Deck: Sequence 3.
  • Continue Slab of Grade Prep & Underground MEP: Area F.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE