Construction Activities for the week ending March 18, 2016

This Week’s Construction Activities

Site/Structure

  • Continue Site Excavation to Grade in at Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Completed PAC Seating Area SOG Pour.
  • Continued Gravel Back Fill & Installation of Water-proofing Along WA & W1 Line.
  • Continued South East Seating Foundation Walls
  • Began Framing Orchestra Seating Slab.

Building

  • Continued Foundation Installation at Office.
  • Continued Backfill of O8 Line
  • Continued Footing prep and pour in Area B1

Parking Deck

  • Continued Column Installation at Southwest Cast-In-Place Deck—Area G
  • Continued additional Deep Foundation Drilled Piers
  • Continued (Final Lift) Shotcrete and Tiebacks at East and West Deck: Area F
  • Continued Erection of Precast Panels for Southwest Private Deck: Sequence 2
  • Poured Slab on Grade Prep in Southwest Private Deck: Area H
  • Commenced Slab of Grade Prep—Area G

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE