Construction Activities for the week ending March 11, 2016

This Week’s Construction Activities

Site/Structure

  • Continue Site Excavation To Grade at Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Completed Radius Concrete Wall Pour & SOG at PAC Orchestra Pit.
  • Continued Gravel Back Fill & SOG Prep in Seating area, between WC—WD lines.
  • Continued Gravel Back Fill & Installation of Water-proofing Along WA Line.
  • Completed Installation of Intermediate Concrete Slab Between Gridlines WX-YB.5

Building

  • Continued Deep Foundation Installation at East Cast-In-Place Deck.
  • Footing prep and pour in Area B1.

Parking Deck

  • Continued Column Installation at Southwest Cast-In-Place Deck: Gridline PA-PG Line All Footings.
  • Continued additional Deep Foundation Drilled Piers: Gridline PCC-PJJ Line
  • Completed (2nd Lift) Shotcrete and Tiebacks at East and West Deck: Grid Line: PCC—PJJ.
  • Continued Erection of Precast Panels for Southwest Private Deck: Gridlines PD-PF.
  • Commenced Slab on Grade Installation in Southwest Private Deck: Gridlines P7-P8.
  • Commenced Slab of Grade Pour: Grid Lines PA-PF.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE

 

Next Week’s Construction Activities

Site/Structure

  • Continue Site Excavation to Grade in at Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Complete PAC Seating Area SOG Pour.
  • Commence Foundation Installation in East PAC – C5 Area. Gridlines: TE.5-ZB.
  • Continue Gravel Back Fill & Installation of Waterproofing Along WA Line.
  • Commence PAC WA Wall 2nd Vertical lift.

Building

  • Complete Deep Foundation Installation at Office.
  • Continue Backfill of O8 Line
  • Continue Footing prep and pour in Area B1.

Parking Deck

  • Continue Column Installation at Southwest Cast-In-Place Deck: Gridline PA-PG Line All Footings.
  • Continue additional Deep Foundation Drilled Piers: Gridline PCC-PJJ Line
  • Complete (3rd Lift) Shotcrete and Tiebacks at East and West Deck: Grid Line: PCC—PJJ.
  • Continue Erection of Precast Panels for Southwest Private Deck: Gridlines PD-PF.
  • Commence Slab on Grade Prep in Southwest Private Deck: Gridlines P7-P8.
  • Commence Slab of Grade Prep: Grid Lines PA-PF.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE