Construction Activities for the week ending April 7, 2016

This Week’s Construction Activities

Site/Structure

  • Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place Deck

Performing Arts Center

  • Completed Gravel Back Fill & Installation of Water-proofing along PAC YB Column Line: East PAC
  • Continued North PAC Foundations: Area C5.
  • Completed 2nd lift of Area C1 Arbor Pit Walls.
  • Continued Gravel Back Fill & Installation of Water-proofing along Studio Theatre East Wall.
  • Completed PAC Stage Wall 2nd Vertical lift.
  • Continued Studio Theater Foundations.
  • Completed PAC Mechanical Room SOG.
  • Began North PAC balcony seating form work.

Building

  • Continued Backfill of O8 Line.
  • Began Continuous Footings at Office Tower.
  • Continue Excavation of Below Grade Elevator Pits.
  • Continue Below Grade Pier Cap Installation.

Parking Deck

  • Continued Column & Shear Wall Installation at Area F Cast-In-Place Deck: All Foundations progressing East.
  • Continue Shotcrete at East Deck: Final Lift.
  • Began Erection of Precast Panels for Southwest Private Deck: Sequence 5.
  • Continued Slab on Grade Prep & Underground MEP: Area F.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.

 

Next Week’s Construction Activities

Site/Structure

  • Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place Deck

Performing Arts Center

  • Complete North PAC Foundations: Area C5.
  • Complete Gravel Back Fill & Installation of Water-proofing along Studio Theatre East Wall.
  • Complete PAC Stage Wall 2nd Vertical lift.
  • Continue Studio Theater Foundations.

Building

  • Continue Backfill of O8 Line.
  • Continue Installation of Continuous Footings at Office Tower.
  • Complete Excavation of Below Grade Elevator Pits.

Parking Deck

  • Continue Column & Shear Wall Installation at Area F Cast-In-Place Deck: All Foundations progressing East.
  • Complete Shotcrete at East Deck: Final Lift.
  • Continue Erection of Precast Panels for Southwest Private Deck: Sequence 5.
  • Commence Erection of Precast Panels for Southwest Private Deck: Sequence 6.
  • Continue Slab on Grade Prep & Underground MEP: Area F.
  • Commence Mid level Deck framing and Re-steel for areas G2 and G3.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE
  • Commencing— Roadwork in Sandy Springs and Mt. Vernon Hwy.