Construction Activities for the week ending April 22, 2016

This Week’s Construction Activities

Site/Structure

  • Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place Deck

Performing Arts Center

  • Completed Gravel Back Fill & Installation of Water-proofing along Studio Theatre East Wall.
  • Completed Balcony Slab installation along North Side of PAC.
  • Commenced Re-Steel installation in North Continuous Footing.
  • Begin Footing East of “YA” Line
  • Continue “W1” Line Wall Pour
  • Continued Re-Steel Installation at 1086’-11” Elevated Slab over Mechanical Room.

Building

  • Continued Excavation & Backfill of O8 Line.
  • Continued Installation of Continuous Footings at Of-fice Tower.
  • Continued Excavation of Below Grade Elevator Pits.

Parking Deck

  • Completed Erection of Precast Panels for Southwest Private Deck: Sequence 6.
  • Completed Mid-level Column installation in Area H
  • Completed Area G3 Mid-Level Deck pour.
  • Commenced Area H1 Lid Deck Formwork & Water-proofing Installation.
  • Commenced Area H3 Mid-Level Column Installation

Roadways

  • Commenced Sandy Springs Circle / Mt. Vernon Hwy Closure.
  • Began Erosion Control installation
  • Began Demo and Grading of Intersection.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.

 

Next Week’s Construction Activities

Site/Structure

  • Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place Deck

Performing Arts Center

  • Complete Gravel Back Fill & Installation of Water-proofing along Studio Theatre East Wall.
  • Commence Re-Steel installation in North Continuous Footing.
  • Complete Footing East of “YA” Line
  • Complete “W1” Line Wall Pour
  • Pour 1086’-11” Elevated Slab over Mechanical Room.
  • Commence Area B1 Studio Theatre Slab on Grade pour.

Building

  • Continue Excavation & Backfill of O8 Line.
  • Complete Installation of Continuous Footings at Office Tower.
  • Complete Excavation of Below Grade Elevator Pits.

Parking Deck

  • Pour Area H1 Lid Level Deck Pour.
  • Commence Area H2 Lid Level Formwork installation at Cast-In-Place deck.
  • Continue Mid-level Column installation in Area H3.
  • Completed Sump-Pit Installation in Area D – West Side of Cast-In-Place Deck.

Roadways

  • Continue Demo and Grading of Mt. Vernon and Sandy Springs Intersection.
  • Began Installation of Storm line piping.

Other

Continue Georgia Power Trenching at Mount Vernon HWY NE.