Construction Activities for the week ending April 15, 2016

Road Closure Alert:  The intersection of Mt Vernon Highway and Sandy Springs Circle takes place on Monday, April 18, 2016.  The intersection will be closed until early summer as crews make needed improvements.  Please visit the Road Work Advisory page for recommended detour options – http://spr.gs/roadwork (the road work button for those with the Sandy Springs Works app – free in the app store).  While the intersection will be closed, the businesses in that area WILL remain open, and would greatly appreciate your continued patronage.

 

This Week’s Construction Activities

Site/Structure

  • Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place Deck
  • Completed North Parcel Grading & Seeding.

Performing Arts Center

  • Continued Gravel Back Fill & Installation of Water-proofing along Studio Theatre East Wall.
  • Continued PAC North Wall Re-steel 2nd Vertical lift.
  • Continued excavation of Studio Theater Continuous Foundations.
  • Complete Reinforcing & Pouring of South Interim Slab at the Mechanical Air Shaft.
  • Complete Reinforcing & Pouring of Trap Slab Extension.
  • Begin Forming & Reinforcing 1086’-11” Elevated Slab Over Mechanical Room.
  • Begin Forming & Reinforcing of North Balcony.

Building

  • Continued Excavation & Backfill of O8 Line.
  • Continued Installation of Continuous Footings at Of-fice Tower.
  • Complete Excavation of Below Grade Elevator Pits.

Parking Deck

  • Complete Shotcrete at East Deck: Final Lift.
  • Completed Erection of Precast Panels for Southwest Private Deck: Sequence 5.
  • Commenced Erection of Precast Panels for Southwest Private Deck: Sequence 6.
  • Continue Slab on Grade Prep & Underground MEP: Area F.
  • Completed Mid level Deck framing and Re-steel for areas G2 and G3.
  • Completed Mid Level Deck Area G2 Concrete Pour.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.
  • Completed Temporary Water line installation along Mt. Vernon, ahead of road work beginning.

 

Next Week’s Construction Activities

Site/Structure

  • Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place Deck

Performing Arts Center

  • Complete Gravel Back Fill & Installation of Water-proofing along Studio Theatre East Wall.
  • Commence Re-Steel installation in North Continuous Footing.
  • Begin Footing East of “YA” Line.
  • Continue “W1” Line Wall Pour.
  • Pour 1086’-11” Elevated Slab over Mechanical Room.

Building

  • Continue Excavation & Backfill of O8 Line.
  • Continue Installation of Continuous Footings at Office Tower.
  • Complete Excavation of Below Grade Elevator Pits.

Parking Deck

  • Complete Erection of Precast Panels for Southwest Private Deck: Sequence 6.
  • Continue Mid-level Column installation in Area H
  • Pour Area G3 Mid-Level Deck.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE
  • Commencing— Roadwork in Sandy Springs and Mt. Vernon Hwy.