Construction Activities for the week April 6, 2017

Construction Activities This Week

Site/Park

  • Continued Forming of Planters, Site Walls & Stair at the City Green.
  • Continued Forming of Plaza & Interactive Fountain.
  • Continued Forming of the Waterwall Fountain.
  • Continued Waterproofing prep of the PAC Fountain.

Performing Arts Center

  • Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.
  • Continued Installation of Exterior Glass/Glazing at North & East Elevation.
  • Continued Landing Prep of North and South Stairs.
  • Continued Fire Protection Installation at the Lower
  • Lobby Level, Box Seating and Lobby Bar.
  • Continued Plaster Installation.
  • Continued East Balcony Ceiling Framing.
  • Continued CE-01 Elevator Installation.
  • Continued Insulation & Ductwork Installation at Lobby Level.

Office Tower & Studio Theatre

  • Continued Framing at Tenant Level.
  • Continued CMU Wall Installation at Service Level.
  • Continued Chiller Plant Piping Installation.
  • Continued MEP Overhead Installation at Govt. Level.
  • Continued Installation of Glass/Glazing.
  • Continued Elevator Installation at Studio Theatre.
  • Continued Roofing Installation at Office Tower.
  • Continued Drywall Installation at Studio Theatre.
  • Continued Installation of Hoods at Kitchen.

CIP Deck

  • Continued Fire Protection Installation.
  • Continued Equipment Room Buildout.
  • Continued Installation & Testing of Fire Alarm Panels.

Roadways/Public Utility

  • Continued Curb & Gutter Install at Sandy Springs East.
  • Continued Sanitary Sewer work at Sandy Springs East.
  • Continued JF Stormwork.

Construction Activities Next Week

Site/Park

  • Continue Forming of Planters, Site Walls & Stair at the City Green.
  • Continue Forming of Plaza & Interactive Fountain.
  • Continue Forming of the Waterwall Fountain.
  • Continue Waterproofing prep of the PAC Fountain.

Performing Arts Center

  • Continue Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.
  • Continue Installation of Exterior Glass/Glazing at North & East Elevation.
  • Continue Landing Prep of North and South Stairs.
  • Continue Fire Protection Installation at the Lower Lobby Level, Box Seating and Lobby Bar.
  • Continue Plaster Installation.
  • Continue East Balcony Ceiling Framing.
  • Continue CE-01 Elevator Installation.
  • Continue Insulation & Ductwork Installation at Lobby Level.

Office Tower & Studio Theatre

  • Continue Framing at Government Level.
  • Continue CMU Wall Installation at Service Level.
  • Continue Chiller Plant Piping Installation.
  • Continue MEP Overhead Installation at Govt. Level.
  • Continue Installation of Glass/Glazing.
  • Continue Elevator Installation at Studio Theatre.
  • Continue Roofing Installation at Office Tower.
  • Continue Drywall Installation at Studio Theatre.
  • Continue Installation of Hoods at Kitchen.

CIP Deck

  • Continue Fire Protection Installation.
  • Continue Equipment Room Buildout.
  • Continue Installation & Testing of Fire Alarm Panels.

Roadways/Utilities

  • Continue Curb & Gutter Install at Sandy Springs East.
  • Continue Sanitary Sewer work at Sandy Springs East.
  • Continue JF Stormwork.