Construction Activities for the week of March 23, 2017

Construction Activities This Week Site/Park Completed Final Tie-in of E-10 Storm Structure. Continued Forming of Planters, Site Walls & Stair at the City Green. Commenced Forming of Plaza & Interactive Fountain. Performing Arts Center Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level. Continued Installation of...

Construction Activities for the week of March 16, 2017

Construction Activities This Week Site/Park Continued Forming of Planters, Site Walls & Stair at the City Green. Continued MEP Installation for the Plaza, Interactive & Waterwall Fountain. Commence Final Tie-in of E-10 Storm Structure. Performing Arts Center Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level....

Construction Activities for the week of March 9, 2017

Construction Activities This Week Site/Structure Completed Final Slab Pour of the PAC Fountain. Continued Forming of Planters, Site Walls & Stair at the City Green. Continued MEP Installation for the Plaza & Waterwall- Fountain. Performing Arts Center Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level....

Construction Activities for the week of March 2, 2017

Construction Activities This Week Site/Structure Continued PAC Fountain Slab Walls and Slabs. Continued Installation of Storm Drainage above CIP Parking Deck. Continued Forming of Planters, Site Walls & Stair at the City Green. Continued MEP Installation for the Plaza Fountain. Performing Arts Center Continued Overhead MEP Rough-in at PAC Lower...

Construction Activities for the week of February 24, 2017

Construction Activity This Week Site/Structure Continued PAC Fountain Slab Prep. Continued Installation of Storm Drainage above CIP Parking Deck. Continued Excavation of Site Walls & Planters at City Green. Continued Pouring of the Footings for the Site Walls & Planters at City Green. Commenced MEP Installation for the Plaza Fountain....

Construction Activities for the week of February 17, 2017

Construction Activities This Week Site/Structure Completed Lower Basin Slab Install for the PAC Fountain. Continued Installation of Storm Drainage above CIP Parking Deck. Continued Excavation of Site Walls & Planters at City Green. Continued Pouring of the Footings for the Site Walls & Planters at City Green. Commenced Layout of...

Construction Activities for the week of February 9, 2017

Construction Activities This Week Site/Structure Completed Pouring of Slip Ramp Walls. Continued Piping Installation for PAC Fountain. Continued Installation of Storm Drainage above CIP Parking Deck. Continued Excavation of Site Walls & Planters at City Green. Commenced Pouring of the Footings for the Site Walls & Planters at City Green....

Construction Activities for the week of February 2, 2017

Construction Activities This Week Site/Structure Continued Elevator Installation at Precast Deck. Continued Piping Installation for PAC Fountain. Continued Installation of Storm Drainage above CIP Parking Deck. Continued Pouring of Slip Ramp Walls. Continued Excavation of Site Walls & Planters at City Green. Performing Arts Center Continued Catwalk and Handrail Backwelding...