Construction Activity Update for the Week of September 21, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP Wall Installation. Continued Installation of Pavers at Shade Bosque and City Green. Continued Construction of the Restroom Building. Continue Flatwork Installation at PAC & Market Square. Performing Arts Center Continued Hanging & Finishing Hard Ceilings. Continued Plaster Installation....

Construction Activity Update for the Week of September 14, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP Wall Installation. Continued Installation of Pavers at Shade Bosque and City Green. Continued Construction of the Restroom Building. Continue Flatwork Installation at PAC & Market Square. Performing Arts Center Continued Hanging & Finishing Hard Ceilings. Continued Plaster Installation....

Construction Activity Update for the Week of September 7, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP Wall Installation. Continued Installation of Pavers at Shade Bosque and City Green. Continued Construction of the Restroom Building. Continue Flatwork Installation at PAC & Market Square. Performing Arts Center Continued Hanging & Finishing Hard Ceilings. Continued Plaster Installation....

Construction Activity Update for the Week of August 31, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP Wall Installation. Continued Installation of Pavers at Shade Bosque and City Green. Continued Construction of the Restroom Building. Continue Flatwork Installation at PAC & Market Square. Continued Installation of Veneer at Waterwall Fountain. Performing Arts Center Continued Hanging...