Construction Activity Update for the Week of April 5, 2018

Construction Activities This Week Site/Park Continued Waterproofing Installation at Waterwall Fountain. Continued Planting at South Parking. Continued Installation of Roof Terrace Waterwall Fountain. Continued Interior Final Pave Operations. Continued Paving at South Parking. Performing Arts Center Continued Installation of PAC Lobby Bar. Continued Completion & Punch List efforts at all...

Construction Activity Updates for the Week of March 29, 2018

Construction Activities This Week Site/Park Continued Waterproofing Installation at Waterwall Fountain. Continued Planting at South Parking. Continued Installation of Roof Terrace Waterwall Fountain. Commenced Completion List at Park. Commenced Interior Final Pave Operations. Performing Arts Center Continued Installation of PAC Lobby Bar. Continued Completion & Punch List efforts at all...

Construction Activity Update for the Week of March 23, 2018

Construction Activities This Week Site/Park Commenced Sub-Slab and Paver Installation at Inter-active Fountain. Continued Waterproofing Installation at Waterwall Fountain. Continued Planting at South Parking. Continued Paver Installation at Arcade. Continued Finish Installation at Shade Structures. Continued Roof Terrace Waterwall Installation and Commenced Waterwall Fountain Installation. Performing Arts Center Continued Installation...