Author Archives: Sarah Wilson

Construction Activities for the Week of August 17, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP Wall Installation. Continued Installation of Pavers at Shade Bosque and City Green. Continued Construction of the Restroom Building. Continued Installation of Sidewalks at Mt.Vernon Hwy. Continue Flatwork Installation at PAC & Market Square. Continued Installation of Veneer at...

Construction Activity Updates for the Week of August 10, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP Wall Installation. Continued Installation of Pavers at Shade Bosque and City Green. Continued Construction of the Restroom Building. Continued Installation of Sidewalks at Mt.Vernon Hwy. Continued Flatwork Installation at PAC. Continued Installation of Veneer at Waterwall Fountain. Performing...

Construction Activities for the Week of August 3, 2017

Construction Activities This Week Site/Park Completed Waterproofing Installation of Waterwall & Plaza and Interactive Fountain. Continued Market Square Fountain Structure and CIP Wall Installation. Continued Installation of Pavers at Shade Bosque and City Green. Continued Construction of the Restroom Building. Continued Installation of Sidewalks at Mt.Vernon Hwy. Continued Flatwork Installation...

Construction Activity Update for the Week of July 27, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP wall installation. Continued Construction of the Restroom Building. Continued Installation of Sidewalks at Mt.Vernon Hwy. Continued Flatwork prep at PAC. Continue Waterproofing Installation at Waterwall Fountain and Plaza Fountain. Performing Arts Center Continued Hanging & Finishing Hard Ceilings....

Construction Activity Update for the Week of July 20, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP wall installation. Continued Construction of the Restroom Building. Continued Installation of Sidewalks at Mt.Vernon Hwy. Continued Flatwork prep at PAC. Commence Waterproofing Installation at Waterwall Fountain. Performing Arts Center Continued Hanging & Finishing Hard Ceilings. Continued Plaster Installation....

Construction Activity Update for the Week of July 13, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP wall installation. Continued Construction of the Restroom Building. Continued Installation of Sidewalks at Mt.Vernon Hwy. Continued Flatwork prep at PAC. Continued Waterproofing prep at Waterwall Fountain. Performing Arts Center Continued Hanging & Finishing Hard Ceilings. Continued Overhead MEP...