Author Archives: Sarah Wilson

Construction Activities for the week of March 23, 2017

Construction Activities This Week Site/Park Completed Final Tie-in of E-10 Storm Structure. Continued Forming of Planters, Site Walls & Stair at the City Green. Commenced Forming of Plaza & Interactive Fountain. Performing Arts Center Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level. Continued Installation of...

Construction Activities for the week of March 16, 2017

Construction Activities This Week Site/Park Continued Forming of Planters, Site Walls & Stair at the City Green. Continued MEP Installation for the Plaza, Interactive & Waterwall Fountain. Commence Final Tie-in of E-10 Storm Structure. Performing Arts Center Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level....

Construction Activities for the week of March 9, 2017

Construction Activities This Week Site/Structure Completed Final Slab Pour of the PAC Fountain. Continued Forming of Planters, Site Walls & Stair at the City Green. Continued MEP Installation for the Plaza & Waterwall- Fountain. Performing Arts Center Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level....

Construction Activities for the week of March 2, 2017

Construction Activities This Week Site/Structure Continued PAC Fountain Slab Walls and Slabs. Continued Installation of Storm Drainage above CIP Parking Deck. Continued Forming of Planters, Site Walls & Stair at the City Green. Continued MEP Installation for the Plaza Fountain. Performing Arts Center Continued Overhead MEP Rough-in at PAC Lower...

Construction Activities for the week of February 24, 2017

Construction Activity This Week Site/Structure Continued PAC Fountain Slab Prep. Continued Installation of Storm Drainage above CIP Parking Deck. Continued Excavation of Site Walls & Planters at City Green. Continued Pouring of the Footings for the Site Walls & Planters at City Green. Commenced MEP Installation for the Plaza Fountain....