Author Archives: Sarah Wilson

Construction Activities for the week of April 20, 2017

Construction Activities This Week Site/Park Completed Forming of Planters, Site Walls & Stair at the City Green. Continued Forming of Plaza & Interactive Fountain. Continued Forming of the Waterwall Fountain. Continued Waterproofing of the PAC Fountain. Commenced Forming of Planters, Site Walls & Stair at the Shade Bosque. Performing Arts...

Construction Activities for the week of April 13, 2017

Construction Activities This Week Site/Park Completed Demobilization of Tower Crane. Continued Forming of Planters, Site Walls & Stair at the City Green. Continued Forming of Plaza & Interactive Fountain. Continued Forming of the Waterwall Fountain. Commenced Waterproofing of the PAC Fountain. Performing Arts Center Commenced hanging Hard Ceilings at East...

Construction Activities for the week April 6, 2017

Construction Activities This Week Site/Park Continued Forming of Planters, Site Walls & Stair at the City Green. Continued Forming of Plaza & Interactive Fountain. Continued Forming of the Waterwall Fountain. Continued Waterproofing prep of the PAC Fountain. Performing Arts Center Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap...

Construction Activities for the week of March 30, 2017

Construction Activities  This Week Site/Park Continued Forming of Planters, Site Walls & Stair at the City Green. Continued Forming of Plaza & Interactive Fountain. Continued Reinforcing of the Waterwall Fountain Performing Arts Center Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level. Continued Installation of Exterior...

Construction Activities for the week of March 23, 2017

Construction Activities This Week Site/Park Completed Final Tie-in of E-10 Storm Structure. Continued Forming of Planters, Site Walls & Stair at the City Green. Commenced Forming of Plaza & Interactive Fountain. Performing Arts Center Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level. Continued Installation of...

Construction Activities for the week of March 16, 2017

Construction Activities This Week Site/Park Continued Forming of Planters, Site Walls & Stair at the City Green. Continued MEP Installation for the Plaza, Interactive & Waterwall Fountain. Commence Final Tie-in of E-10 Storm Structure. Performing Arts Center Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level....

Construction Activities for the week of March 9, 2017

Construction Activities This Week Site/Structure Completed Final Slab Pour of the PAC Fountain. Continued Forming of Planters, Site Walls & Stair at the City Green. Continued MEP Installation for the Plaza & Waterwall- Fountain. Performing Arts Center Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level....

Construction Activities for the week of March 2, 2017

Construction Activities This Week Site/Structure Continued PAC Fountain Slab Walls and Slabs. Continued Installation of Storm Drainage above CIP Parking Deck. Continued Forming of Planters, Site Walls & Stair at the City Green. Continued MEP Installation for the Plaza Fountain. Performing Arts Center Continued Overhead MEP Rough-in at PAC Lower...